Strengthening the Local Electric Grid

RIKY Transmission Project

A public transmission line project being developed by Republic Transmission (Republic), in collaboration with Big Rivers Electric Corporation (Big Rivers) to meet a need defined by the Midcontinent Independent System Operator (MISO).

After a multi-year planning process and advocation by Big Rivers, MISO approved the RIKY transmission project to build resiliency and improve electric grid reliability in western Kentucky.

In 2025, MISO conducted a competitive solicitation process for the RIKY transmission project and selected Republic as the lowest-cost proposal to develop RIKY.

RIKY is an infrastructure improvement project that does not involve new generation or new large loads.

RIKY is a single-circuit 345 kV overhead transmission line connecting the Reid Substation in Webster County, KY to the Kentucky-Indiana state line. The proposed route is predominantly located in eastern Henderson County. CenterPoint Energy is responsible for the Indiana portion of the transmission line. This transmission project will improve electric grid infrastructure in western Kentucky.

Community Benefits

Steel truss railroad bridge over the Ohio River

Invests in Kentucky

~$75+ million of new infrastructure to improve the flow of electricity for western Kentucky.

Stabilizes Prices

Supports more stable, affordable electricity prices for homes, farms and businesses in Henderson County and the surrounding region.

Elevates Communities

Taxes paid help to fund essential public services like roads and schools, while providing construction jobs and donations for local causes.

Map

RIKY transmission line project map showing the proposed route and alternative route segments between Reid Substation and the IN/KY endpoint

The final route has not been selected. View or download the full-size map (PDF)

Timeline

  1. 2022
    MISO Launches its 2024 Transmission Improvement Plan
  2. 2024
    MISO Approves Transmission Improvements for Tranche 2.1, Including RIKY
  3. 2025 – 2026
    MISO Planning and Selection Process
  4. 2026 – 2028
    Stakeholder Engagement, Permitting and Real Estate Work
  5. 2028
    Anticipated Start of Construction
  6. 2030
    Anticipated Energization

Community-Focused Approach

Republic Transmission believes in the importance of building strong, long‑term relationships in the communities where our projects are located.

  • The project team will meet with landowners and stakeholders, provide information, explain the process and gather feedback before major decisions are finalized.
  • The RIKY Project will create nearly 70 jobs during construction, generate over $90 million in regional economic output and provide millions in tax revenue over the project’s life to help fund essential local services.
Republic Transmission team members talking with residents at a RIKY project open house in a barn

Updates

Current Status

The project team is currently in the early stages of development and local outreach. The current focus is engagement with community landowners and stakeholders, to share project information, listen to and answer questions, and receive feedback about the project and proposed route.

Community participation is an important part of the development process and we encourage community engagement.

Please check back on this website for updates and project information.